Update: 124th Avenue Extension Project


                                                  FY 2017–18 saw the beginning of the end of the 124th Avenue
                                                  Extension Project. The $33 million project is expected to be largely
                                                  complete by late 2018—following 10 years of planning, public com-
                                                  ment, meetings and an additional three years of construction.

                                                  An impressive 12,800 feet of Willamette Water Supply Program

 Basalt Creek Parkway 2017  SW Grahams Ferry Road 2017  (WWSP) pipeline was installed on 124th Avenue in FY 2017–18, as
                                                  the collaborative road construction and pipeline installation project
                                                  moved towards completion.

                                                  Renus Kelfkens, Project Manager, said other work completed in FY
                                                  2017–18 included:

                                                      » August 2017: Completion of Basalt Creek Parkway,
                                                     a new 0.7-mile arterial connecting SW Tonquin Road
                                                     and SW 124th Avenue to Grahams Ferry Road.

                                                      » April 2018: Construction of right-turn lanes from
                                                     Tualatin Sherwood Road onto 124th Avenue.

                                                      » June 2018: Tonquin Road widened to three
                                                     lanes, between Basalt Creek Parkway and
                                                     Grahams Ferry Road.

                                                      » June 2018: Improvements to the Tonquin Road rail
                                                     crossing, which carries TriMet’s WES Commuter Rail.

                                                  Work completed in FY 2018–19 included:
                                                      » August 2018: Installation of an additional
                                                     1,250 feet of WWSP pipeline.

                                                      » October 2018: Widening of Grahams Ferry Road,
                                                     between Day and Tonquin roads.

                                                      » October 2018: Improvements to the Grahams Ferry
                                                     and Tonquin roads intersection.
 124th Avenue 2018  124th Avenue 2018
                                                  The 124th Avenue Extension will open to traffic by late 2018.