lower the groundwater level. This section of road has seen significant
settlement over time, due to the slide’s continual movement toward
the lake.
Phase Two was completed in fall 2018. It was a long time coming,
Cruise said. But it was worth the wait.
“To see the transformation from broken roads and potholes to smooth
surfaces is incredible,” he said. “I’m eager for the third and final phase
to begin.”
Phase Three will begin in fall 2019 and focus on stabilization of the
Scoggins Valley Road landslide near Stepien Road.
“Once this project is complete, residents and tourists alike will
enjoy new smooth driving and biking surfaces around the entire lake,”
Cruise said.
The Hagg Lake Perimeter Roads project’s total cost is estimated at
$20 million. The Federal Lands Access Program (FLAP) is funding
about $10 million; the balance is coming from Washington County.
SCOGGINS VALLEY RD
Phase Two started in fall of 2017. Hankins Road landslide stabilization, feet. For two years, Hankins was A deep patch was constructed to fix WES T SHORE DR Hagg Lake
Work included stabilization of three in particular, has been a significant home to two-way traffic on a one- a noticeable dip in the roadway, and WEST SHO RE DR DAM
landslides, replacement of three improvement. The Hankins slide has lane section of road. The work to work was completed in June 2018.
culverts, guardrail upgrades been impacting West Shore Drive rebuild the failed lane was com- The third landslide on West Shore
and paving. ever since the roadway was built in pleted in late 2017. Drive, north of Scott Hill Road, cre-
the 70s.”
“This work was more noticeable Work on the second landslide sta- ated uneven roadway surfaces, Road Maintenance Phases
because of the amount of dam- In late 2013, the Hankins Road land- bilization, on West Shore Drive potholes, cracks and poor driv-
age multiple slides had inflicted on slide caused nearly 500 feet of the between Hankins and Scott Hill ing conditions. Work included the
West Shore Drive,” Cruise said. “The northbound lane to drop about 4 roads, kicked off in spring 2018. installation of horizontal drains to
19 | Partnering for the Future LUT Annual Report FY 2017–18 LUT Annual Report FY 2017–18 Partnering for the Future | 20