124th Avenue Extension





 project reaches milestones




















     By Heather Sturgill,
     Senior Communications Specialist/PIO


     It’s been another great year for the SW 124th            Basalt Creek Parkway, a new 0.7-mile arterial
     Avenue Extension with several important                  connecting SW Tonquin Road and SW 124th
     milestones achieved.                                     Avenue to Grahams Ferry Road, is the most
                                                              significant part of the project completed to
     “The 124th Avenue Extension project is one of the        date. The road opened in August 2017. At the
     most exciting projects I’ve been able to work on,”       same time, Tonquin Road closed between
     said Renus Kelfkens, Project Manager, Engineering        Grahams Ferry Road and 124th Avenue for
     and Construction Services Division. “With two            widening and WWSP pipeline installation.
     new roads being built, a partnership with the            Tonquin is expected to reopen in April.
     Willamette Water Supply Program (WWSP)
     pipeline and support from the community,                 “Basalt Creek Parkway is designed to expand
     it’s just wonderful to go to work every day              to five lanes, which will be done in the future by
     and see progress being made.”                            developers,” said Kelfkens. “It’s not often we can
                                                              build a completely new road and incorporate so
     The 124th Avenue Extension will provide a new            much anticipated growth.”
     connection between Sherwood, Tualatin and
     Wilsonville; access to the Basalt Creek area;            Grading for the 124th Avenue Extension was
     and an additional connection to I-5 and Hwy              completed in August 2016. Two large retaining
     99W. In addition to extending 124th Avenue from          walls, created by drilling long metal rods into
     Tualatin-Sherwood Road to Tonquin Road, both             the embankment and reinforcing it with concrete,
     Grahams Ferry Road (between Tonquin and Day              were completed on sections of 124th Avenue and
     roads) and Tonquin Road (between 124th Avenue            Tonquin Road where the road was cut through
     and Grahams Ferry Road) will be widened to               rocky, basalt terrain. The 20- and 30-foot walls
     include center turn lanes and wide shoulders.            were reinforced with steel and covered with


                                                                                              Continued on page 11