Defining Capacities for an Individual Part
Previous Topic  Next Topic 

The reported maximum capacity for an individual part is the volume of this part that can be produced given the working times defined. 


To define the capacity for an individual part:


  1. Click the Capacity Input tab:
  2. Enter your Reported Max Capacity with appropriate units of measure selected.  Yellow indicates a required field.
  3. Enter Shifts per Week. 
  4. Enter Hours per Shift. 
  5. Enter Days per Week. 
  6. Enter Weeks per Year. 
  7. Enter the Reported Date by clicking the today button or if reported date is other than today's date use the calendar icon. The reported date identifies when the capacity has last been updated.
  8. Click Calculate to view annual capacity results. See Calculator Tool. 
  9. Click the Resource Constraints tab to proceed to the next step. Defining Resource Constraints for an Individual Part.