Using premium backup and recovery services : Backup Lifecycle Management (BLM) : Configuring a BLM schedule
 
Configuring a BLM schedule
You can create a new BLM schedule (or edit an existing Schedule by adding a detail to copy files to BLM).
Use the Perform BLM detail with the Enforce Retention detail to set the policies for handling backed up data.
1. In the Backup Schedules tree, select the required backup schedule.
2. On the Schedule menu, click Edit Schedule.
F1 Help: "Schedule"
3. In the Details section, select New to create a new detail.
4. Select Perform BLM.
5. Beside Perform BLM, click the [>>] button.
The Select BLM Options dialog box appears.
F1 Help: "Select BLM Options"
6. Use these settings to configure what will be archived, and how BLM will handle the data when this schedule is run.
7. Click OK and then Save.
Scheduling a backup set for BLM:
Assign the BLM Schedule to the required backup set(s).
The backup set(s) do not have to be configured with the BLM (Infinite Generations) option.
1. In the Backup Sets tree, select the required backup set.
2. On the Sets menu, point to Backup Sets, and then click Properties.
3. In the Backup Set Properties dialog box, click Schedule.
4. On the Schedule tab, select a Schedule, and then click OK.