The maximum model usage refers to the maximum number of parts that will be used at a particular linefeed across all models per hour.
MMU = maximum number of parts per model * line rate
For example
given a takt time = 300 secs
If a production line is running a 100 % capacity then the line rate = 12 models per hour
(1 model/ 300 sec * 60 sec/min *60 min/hr)
If the maximum part per model as specified in the BOM is equal to 1 across all models using that point of use then
MMU = 1 max part /model * 12 models /hr= 12 max parts /hr
Maximum Model Usage is a rough estimate for calculating maximum Kanban loop size. The appearance of the MMU on the Point of Use Details session is controlled by a system parameter.