Managing an N1 configuration : Stopping an N1 node
 
Stopping an N1 node
The N+1 Status dialog box gives you a visual display of current status of the N+1 configuration.
To stop an N+1 node:
1. On the N + 1 menu, click Status.
F1 Help: "N + 1 Status"
2. Click the List tab to view a display of the System Backup Summary information, sorted by node.
3. To stop a node (stop the DS-System service on that node), select the node you want and click Stop Node. The Stop N+1 Node dialog box appears.
F1 Help: "Stop N + 1 Node"
4. Select how to handle current activities on the DS-System:
Wait for all running activities to complete: Stops the DS-System on the selected node after all the current activities have completed. No new activities will be allowed once you click OK.
Stop when all activities complete or force stop after [...] minute(s): Stops the DS-System on the selected node after all the current activities have completed, or force a stop after the specified time has elapsed. No new activities will be allowed once you click OK.
5. Click OK.
IMPORTANT:  Once you stop a node, it cannot be restarted from DS-Operator. If you stop the node that is currently the DS-Director, the N+1 will have to reform.
You can view the change in the N+1 Status dialog box.