In this Industry Current, originally published in Power Finance &
Risk, three attorneys at Orrick discuss the
evolution of the U.S. Department of
Defense's power procurement process and the implications for
sponsors seeking DoD power purchase agreements. The authors are Harry
L. Clark, a partner in the firm's international trade
and compliance group, Christopher
Gladbach, a partner in the energy and infrastructure
group, and Evgeniya
Shakina, an associate in the international trade and
compliance group.
The U.S. Department of Defense and each of the three major
military service branches are committed to expanding renewables
purchases to meet their energy needs over the next decade. The
National Defense Authorization Act of 2007 requires that DoD procure
25% of its energy from renewable sources by fiscal year 2025. In
2012, President Barack Obama buttressed this goal by
announcing a 2025 renewables deployment goal of 3 GW for DoD.
The service branches have each made significant progress in
purchasing renewables from utility-scale projects, including from
off-base and on-base (behind-the-meter) projects.
To accelerate this progress, to varying degrees, they are now
exploring larger-scale procurements by relying on government
procurement offices such as the Defense Logistics Agency. In
expanding the scope of renewables purchases, they are moving to a
more comprehensive "systems installation" approach as well as
aggregation of several projects (for service to multiple locations)
in one solicitation.
These approaches could involve a combination of on-site and
off-site generation, micro-grids and, potentially, energy storage
facilities. While creating an interesting opportunity for
developers, the move to "systems installation" and
project-aggregation approaches creates certain challenges beyond the
usual set of risks related to government contracting that developers
and financing parties need to consider. This article highlights some
of those key issues as well as other unique issues and risks
associated with these types of projects.
Project Timing and Coordination
The government does not act like a private party in procuring
goods and services. In general, (1) the government is often slow,
and delays are frequent; (2) government approvals take time and
necessitate coordination among a number of parties; and (3) apart
from a few persons inside specialty agencies, the government has
little experience or expertise relating to renewables projects or
third-party project finance.
As an example of the approval and coordination challenges, for a
typical behind-the-meter solar project, the developer may have to
negotiate a PPA with one government agency and a site-land lease
with another; the developer will also need the support of the
relevant installation leadership. This same developer will then have
to get approval of the PPA package from the Office of the
Secretary of Defense, which, if not coordinated appropriately,
can result in significant additional delay.
That said, DoD has gained broad experience recently on renewables
projects and has learned some lessons. Each new project takes less
time and involves fewer government-specific challenges than the
last. DoD agencies are proceeding in a more coordinated way.
Agencies such as DLA that have already been in charge of multiple
contracts have significantly improved their relevant processes over
the last several years and reduced project delays (but, of course,
there is room for further improvement).
In pursuing amalgamated projects for multiple installations, the
service branches will need to take special care in ensuring that the
multiple projects are coordinated centrally and the approval process
is streamlined. Otherwise, the risk of a development delay may be
too high for a developer to absorb.
Guaranteed Energy Purchases and Minimum Annual
Production
Most DoD PPAs include commitments that the government as the
power purchaser will pay for a minimum annual production level per
year. Beyond this level, the DoD typically commits only to pay for
energy consumed rather than the total volume of energy produced by
the asset (common in the utility PPA market).
For behind-the-meter projects in states without net metering
schemes, this effectively means that developers will only build
projects that meet the minimum annual guaranty level since there are
no assurances that additional generation will be paid for.
For off-site facilities, the developer should have a plan and
obtain requisite permits and approvals to sell the energy in excess
of the government's consumption in the relevant market.
In parallel, developers generally have to pay liquidated damages
to the government if generation does not meet a certain minimum
annual production threshold. When negotiating these thresholds,
developers should ensure that they allow enough breathing room for
project underperformance.
As the government moves to thinking about multiple projects
serving multiple loads, these thresholds will continue to assume
paramount importance and invite scrutiny by financing parties.
Portfolio Risk
Aggregating multiple energy projects to serve multiple loads
creates unique portfolio-associated risk, which needs to be
mitigated. Financing parties will seek comfort that multiple
projects are sufficiently isolated such that a problem or delay
involving one energy project does not jeopardize the revenue from
the contract as a whole. Thus, developers and the government will
both have to think about how to structure these procurements,
including considering events of default and provisions related to
single-project terminations (as opposed to overall contract
termination).
One method that has been considered is the right to "off-ramp" or
"shelve" a project if there is a significant development delay or
hurdle to allow the rest of the projects to proceed while parties
continue to seek to resolve challenges associated with the shelved
project.
State Utilities Laws
State utility laws are critically important for the viability of
any given DoD project. For example, a solution involving both
on-site and off-site generation delivered to one or more retail
loads would only be possible in states that have sufficiently
deregulated the energy market and have retail choice (absent some
type of a back-to-back or other arrangement with a utility). At the
same time, behind-the-meter projects may have limited potential in
states that do not allow net metering unless (1) they are
sufficiently small such that their output is almost always less than
the load of the installation or (2) an appropriate storage facility
is created for excess energy.
Also, state utilities laws could impact the structure of the
developer's offer. For example, in Texas's deregulated market, the
legal owner of generation assets cannot act as a retail electric
provider, which necessitates some additional considerations by the
developer with respect to structuring the project if a physical load
is to be served by the developer's generating asset.
Termination for Convenience
In federal procurement of goods and services—including for
energy—the government must have the right to terminate the
procurement contract for the government's "convenience," that is,
without justification.
As a result, developers and financing parties are often concerned
about the uncertainty of their recovery in the event of termination
for convenience. One solution is a tailored termination for
convenience contract clause that references a standard schedule for
party recovery defining the level of recovery for every year during
construction and following commercial operation of the relevant
project—often called a termination value schedule.
The negotiated termination for convenience contract clause should
also account for distributions to all financing parties, including
debt and potential tax equity investors, applicable upon a
termination settlement. developer will have to take care to include
other allowable costs that result from a termination in the contract
clause, including make-whole costs for debt repayment and associated
penalties and fees, interest rate hedging breakage costs,
personnel-related demobilization costs and costs associated with
pursuing a termination settlement with the government.
Anti-Assignment Act and Financing
Consents
The Anti-Assignment Act generally prohibits assignment of a
federal procurement contract without the consent of the government.
This creates tension related to the rights of a lender to "step-in"
and assume the contract in a default scenario.
To overcome the general ban on contract assignment, the
government requires that its acquiescence to an assignment be
memorialized in a novation agreement between the government, the
contractor and the party to whom the contractor is assigning the
contract.
The novation approval process represents additional risk and
uncertainty that financing parties must accept. The government can
agree to mitigate this risk by allowing financing parties to cure
developer defaults through payment of money, and pledges of upstream
equity in the project company owning the renewables project are
generally permitted.
Developers and financing parties should generally account for
additional time and resources needed to negotiate estoppels and
financing consents with the government as such consents often are
not initially developed or standardized and take time to
negotiate.
Changes and Subcontracting
Under developer "prime" project contracts with the government,
developers are necessarily acting as a conduit between DoD and
subcontractors, and, thus, their obligations to perform under a
prime contract should be fully supported by subcontractors'
obligations to perform under their respective subcontracts.
With limited exceptions, DoD may make "changes" within the
general scope of its contract at any time, resulting in increased
costs to the developer. Developers have contract rights to higher
upward contract price adjustments to offset cost increases
attributable to changes. But the risk of a government short-pay of
an equitable adjustment request needs to be appropriately allocated
between the developer and its subcontractors.
One method to alleviate developer risk related to changes is to
include "pay-if-paid" arrangements pursuant to which the
subcontractor gets made whole only if price adjustments fully
account for increased costs. There are a number of alternative
risk-allocation methods that developers and subcontractors utilize.
The developer should also be sure to properly "flow down" certain
rights and obligations related to federal acquisition regulations to
its subcontractors.
Leases
As mentioned in Part I, for on-site projects at a military
installation, the developer will need to negotiate a lease with the
government in its role as the landowner.
Government lease forms, which were inevitably created for
unrelated purposes such as housing for service personnel, ordinarily
require substantial tailoring to serve as reasonable lease
arrangements and facilitate financing. It is critical that the
developer evaluate lease forms' treatment (or non-treatment) of
issues such as lender protections and step-in rights, allocation of
risk related to environmental liability, insurance, government
property-related access restrictions and lessee indemnification.
Assuming that the trend related to the utilization of multiple
on-site projects continues, the government should pursue (and
developers should request) a centralized approach to lease
negotiations to mitigate time and resource costs attributable to
work with standard DoD lease forms. Happily, DoD has recently
negotiated several leases for renewables projects with relatively
sophisticated developers, so the government now has access to better
precedent. It is to be hoped that these improvements come to be
reflected in DoD lease forms.
Buy-American/Domestic Preference
Rules
Domestic preference rules apply to utilization of solar panels
for DoD power projects. Solar panels must be sourced from the U.S.
or another "designated or qualifying country." Designated and
qualifying countries include parties to the World Trade
Organization Procurement Agreement and countries that have a
free trade agreement or qualifying defense procurement arrangements
with the U.S.
Notably, China is not party to any of these arrangements, meaning
that solar panels for DoD projects generally cannot be sourced from
China. Developers must, therefore, consider opportunities for
utilizing panels from other countries and potential implications of
the use of such panels for project economics. |